Feb 12th, 2020

Innolith has completed the technology trials of its new interconnection and battery management system technology.  The trials were conducted in a live production environment on the 1.2 MWh GridBank located in Hagerstown, Maryland.  A year long, $1 million upgrade saw the original cell interconnect technology updated and the battery management system upgraded which has led to the GridBank receiving a PJM Performance rating of over 95%.

Following the success of the trials in Hagerstown, Innolith will now be seeking a commercial partner to take over ownership and management responsibility for the GridBank.